Friday, September 24, 2010

My Notes on PgMP exam

In this post I am sharing some quick notes for Project Management Institute (PMI)’s Program Management Professional (PgMP) credential Exam. These notes are specifically based on Standard for Program Management V2.

I have shared colored Inputs, Outputs, Tools & Techniques (ITTOs) for all Knowledge Areas in Box.net under http://www.box.net/shared/f7bk0e5psf

NOTES:
1. Project: Project is defined as a temporary endeavor undertaken to create a unique product, service or result

2. Project Management: Project management is the application of knowledge, tools, skills and techniques to project activities to meet the project requirements

3. Program: A program is a group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually
(Or)
A program is comprised of multiple related projects that are initiated during the program’s life cycle and are managed in a coordinated fashion

4. Program Management: Program management is the centralized coordinated management of a program to achieve the program’s strategic objective and benefits It involves aligning multiple projects to achieve the program goals and allows for optimized or integrated cost, schedule and effort

5. Program manager coordinates efforts between projects but does not directly manage the individual projects

6. Essential program management responsibilities include
  • The identification, monitoring and control of the inter-dependencies between the projects;
  • Dealing with the escalated issues among the projects that compromise the program; and
  • Tracking the contribution of each project and the non-project work to the consolidated program benefits
7. Projects within a program are related through a common outcome or a collective capability that is delivered

8. If the relationship among projects is only that of a shared client, technology, seller or resources, the effort should be managed as a portfolio of projects rather than as a program

9. Portfolio: A Portfolio is a collection of components (i.e. projects, programs, portfolios and other work such as maintenance and related ongoing operations) that are grouped together to facilitate the effective management
of that work in order to meet the strategic business objectives
(Or)
A Portfolio is a set of Projects or Programs or both that is managed in a coordinated fashion to obtain control and benefits not obtained from managing them individually

10. The projects or programs of the portfolio may not necessarily be interdependent or directly related

11. During the early phases of initiating and planning, information flows from the program to the components, and then flows from the components to the program in the later phases of planning and in the executing, monitoring and controlling, and closing

12. Early in the lifecycle, the program guides and directs the project domain on desired goals and benefits. The program domain also influences the approach for managing the individual projects within it. Later in the lifecycle, the project domain reports to the program domain on project status, risks, changes, costs, issues and other information affecting the program

13. Like the interactions between program and project domains, portfolio management and program management domains interact in their process groups

14. If the Organization is actively managing its portfolio, the program’s initiating and planning process groups receive inputs from the portfolio domain. These inputs include strategic goals and benefits, funding allocations, requirements, timelines and constraints that the program team translates into the program scope, deliverables, budget and schedule

15. A portfolio is one of the truest measures of an Organization’s intent direction, and progress. It is where investment decisions are made, resources are allocated, and priorities are identified

16. The distinctions among portfolio, program and project management can be made clearer through their interaction

17. Portfolio management focuses on assuring that programs and projects are selected, prioritized and staffed with respect to their alignment with Organizational strategies

18. Program management focuses on achieving the benefits aligned with the portfolio and subsequently with Organizational objectives

19. Programs are comprised of projects that focus on achieving their individual requirements

20. The program management office (PMO) is a crucial portion of the program’s infrastructure. The PMO supports the program manager with the management of multiple, unrelated projects

21. PMO provides support to the program manager by
  • Defining the program management processes that will be followed,
  • Managing schedule and budget at the program level,
  • Defining the quality standards for the program and for the program’s components,
  • Providing document configuration management, and
  • Providing centralized support for managing changes and tracking risks and issues
22. Enterprise environmental factors can significantly impact on the program’s management and its ultimate success. They include but not limited to
  • Organizational structure, culture and processes
  • Government or industry standards (Regulations, quality standards)
  • Infrastructure (Existing facilities & capital equipment)
  • Existing human resources
  • Personnel administration (Staffing/retention policies, etc)
  • Company work authorization systems
  • Market place conditions
  • Stakeholder risk tolerances
  • Political climate
  • Organization’s established communication channels
  • Commercial databases
  • Project Management Information System
23. Organizational process assets, which include any or all processes related to the assets, can influence the program’s success

24. Process assets include the Organization’s knowledge bases such as best practices, lessons learned & historical information, such as completed schedules, risk data and earned value data

25. The program begins either when funding is approved or when the program manager is assigned

26. Program manager must have strong communication skills to deal with various stakeholders – team members, sponsors, managing directors, customers, vendors and senior management, and other program Stakeholders

27. Five main phases of a program life cycle are

  • Pre – program preparations
  • Program initiation
  • Program setup
  • Delivery of program benefits
  • Program closure
28. Program life cycle complies with the needs of corporate governance and also ensures that the expected benefits are realized in a predictable and coordinated manner.

29. Benefits management requires the establishment of processes and measures for tracking and assessing benefits throughout the program life cycle

30. The pre-program work focuses on the analysis of the available information about organizational and business strategies, internal & external influences, program drivers and the benefits that involved parties expected to realize

31. Range of activities in pre-program phase includes (UDDDA)

  • Understanding the strategic benefits of the program,
  • Developing a plan to initiate the program,
  • Defining the program objectives and their alignment with the organizational goals,
  • Developing a high level business case demonstrating an understanding of the needs, business benefits, feasibility and justification of the program,
  • Agreeing to “check points” throughout the program, to ensure its on track
32. The program initiation phase’s primary objective is to develop in greater detail how a program can be structured and managed to deliver the desired outcomes that were identified in the program mandate

33. Program Charter is the formal document that consolidates all the available information about the program. Its contents generally are
  • Justification
  • Vision
  • Strategic Fit
  • Outcomes
  • Scope
  • Benefit Strategy
  • Assumptions & constraints
  • Components
  • Risks & issues
  • Time scale
  • Resources needed
  • Stakeholder considerations
  • Program governance and
  • Initial high-level roadmap
34. Program Charter is the primary document analyzed by the strategic governing body to decide if the delivery of the program is approved. Once approved, program charter provides the basis of the progress to program setup, the development of the program’s full business case, detailed program plans, and component charters

35. Typically following factors are considered when selecting and approving programs
  • Desired outcomes
  • Benefits analysis, which identifies and plans for their realization
  • Strategic fit within the organization’s long term goals
  • Total available resources (Eg: funding, equipment or people)
  • Estimated time scale, costs, and effort required to set-up, manage and deliver the program and
  • Risks inherent in this program
36. The activities in program initiation phase include
  • Approval from the strategic governing board to proceed to the next program phase (program setup)
  • Program charter or program mandate that documents, for example
  • Vision, key objectives and success criteria
  • Expected outcomes and benefits
  • Program assumptions and constraints
  • High-level program plan and
  • Known risks and issues
  • Identifications of suitable business change managers with the ability to influence business change
  • Identification of potential members of the sponsoring group or program board
  • Identification of key decision makers/stakeholders in the program and their expectations and interests
  • Identification of candidate projects and other potential program components
  • Appointment of the executive sponsor and the program manager
  • Creation of the infrastructure to manage the program and
  • Identification and commitment of key resources needed for setting up the program
37. In the Program setup phase, the program has received the “approval in principle” from a selection committee

38. In the Program setup phase, a program manager has been identified, and the key input into this phase – a program brief or charter defining high-level scope, objectives, visions and constraints has been generated

39. Purpose of program setup phase is to progressively elaborate the program charter and develop the foundation for the program by establishing an infrastructure and building a detailed “roadmap” that provides direction on how the program will be managed and defines its key deliverables

40. Program management plan contains answers to the following questions

  • What is the end result and expectations?
  • When will it be ready and accomplish the program benefits?
  • What will be the program budget?
  • What are the risks and issues?
  • What dependencies, assumptions and constraints?
  • How will the program and program components be managed?
  • What are the other services required?
  • How will the program be managed/executed?
41. The activities in program setup phase include
  • Aligning the vision, mission and values for the program with the organization’s objectives
  • Developing an initial detailed cost and schedule plan for setting up the program and outline plans for the reminder of the program
  • Conducting feasibility studies, where applicable, to assess the proposed program for technical and economic feasibility, as well as ethical feasibility or acceptability
  • Establishing rules for make/buy decisions as well as those for selecting subcontractors to support the program
  • Developing a program architecture that maps out how the projects within the program will deliver the capabilities that results in the required benefits
  • Developing a business case for each of the project in the program which addresses the technical, investment and regulatory/legislative factors which may pertain to each project and
  • Communicating with stakeholders and getting the support
42. Key results from program setup revolve around the program-level planning processes
  • Scope definition and planning
  • Requirements definition, decomposition, validation and management
  • Benefits definition, decomposition, management, cost and realization
  • Activity definition and sequencing
  • Duration estimates
  • Schedule
  • Procurement of external resources
  • Contracting and procurement
  • Human resources and staffing
  • Cost estimates/budgeting
  • Risk management consolidation
  • Constituent component identification and definition
  • Program management office to support the program
  • Approval of the program management plan, based upon the individual business cases and supporting feasibility studies
  • Program governance mechanism with approval and reporting procedures
  • Program control framework for monitoring and controlling both the projects and the measurement of the benefits within the program
  • Facilities and other required infrastructure to support the program and
  • IT systems and communication technologies with the necessary support arrangements to sustain the program throughout its life cycle.
43. The purpose of delivery of program benefits phase is to initiate the component projects of the program and manage the development of the program benefits, which were identified during the initial phases

44. The delivery of program benefits phase ends when the planned benefits of the program are achieved, delivered and accepted or a decision is made to terminate the program


45. The activities in this phase include
  • Establishing a project governance structure to monitor and control the projects
  • Initiating projects in order to meet program objectives
  • Ensuring component deliverables meet the requirements
  • Analyzing progress to plan
  • Identifying environmental changes which may impact the program management or its anticipated benefits
  • Ensuring that shared resources, common activities and other dependencies across the components are coordinated
  • Identifying risks and ensuring appropriate actions have been take to manage positive and negative risks
  • Identifying issues and ensuring corrective actions are taken
  • Measuring benefits reutilization
  • Reviewing change requests and authorizing additional work as appropriate
  • Maintaining thresholds and initiating corrective action when results are not delivered per expectations and
  • Communicating with stakeholders and with the program governance board
46. Purpose of program closure phase is to execute a controlled closedown of the program

47. Activities of program closure phase lead to the shutdown of the program organization and infrastructure

48. For many programs, the product is delivered and/or accepted to the customer and the program is shut down

49. For other programs, the product transitions into an operational phase and is managed by normal operations

50. The activities in this phase include
  • Review status of benefits with the stakeholders
  • Disband the program organization
  • Disband the program team and ensure arrangements are in place for appropriate redeployment of all human resources
  • Dismantle the infrastructure and ensure arrangements are in place for appropriate redeployment of all physical resources (facilities, equipment, etc)
  • Provide customer support assuring that guidance and maintenance will be provided in the event that an issue arises or a defect is detected in the program after its delivered and accepted by customer. The
    assurance is generally defined by contract
  • Document lessons learned in the organizational database so that they can be referred in the future for similar programs.
  • Provide feedback and recommendations on the changes identified during the program’s life but beyond the scope of the program that may benefit the organization to pursue
  • Store and index all program related documents to facilitate reuse in the future or possible future audits and
  • Manage any required transition to operations
51. Program governance oversees the progress of program and the delivery of the coordinated benefits from its components. Implementation of program governance is critical for the success of a program since it is difficult by an individual to manage complex programs

52. Program governance assists in managing risks, stakeholders, benefits, resources and quality across program life cycle

53. The phase-gate review approach is focused on strategic alignment, investment appraisal, monitoring & controlling of opportunities and threats, benefits assessment and monitoring program outcomes

54. Phase-gate reviews are recommended to assist program control & management as well as to facilitate program governance

55. Phase-gate reviews are carried out at key decision points in the program life cycle

56. Each phase-gate review functions as a “go” or “no-go” decision point on the program as a whole

57. A phase gate review is performed to check the program performance against the planned criteria for exit from the phase that has just been completed, and to determine the readiness for proceeding to the next phase

58. A strategic decision-making body in the form of portfolio review board or executive steering group may issue a program mandate, which defines the strategic objectives and benefits that the program is expected to deliver

59. A benefit is an outcome of actions and behaviors that provides utility to the Organization

60. Unlike projects, which usually delivers all the benefits at the end of the project, programs can deliver benefits either all at once at the end of the program or incrementally during the program itself

61. Benefits realization planning is part of program initiation phase and is one of its main outputs

62. The Benefits realization plan is a very crucial output item of the Initiate Program process, as it is used in establishing the feasibility of the program and obtaining funding

63. Benefits realization planning is part of Program management plan and helps to determine how benefits will subsequently be realized as well as providing a baseline for tracking progress and reporting any variance

64. A process is a set of interrelated actions and activities performed to achieve a pre-specified outcome

65. Program management processes addresses issues at a higher level and involve less detailed project level analysis

66. Similar to project management processes, program management processes require coordination with other functional groups in the Organization as well as stakeholder management in general – but in a broader context

67. Processes receive inputs from processes that logically precede them and send outputs to successor processes. In some cases, an output from the process becomes an input to the same process
Example: When a planning process iteratively updates a plan over time

68. The complexity of program management process model is increased when inputs and outputs flow between the project domain, the program domain and the portfolio domain

69. There are common inputs & outputs to most program management processes
  • Assumptions (Input & Output)
  • Constraints (Input)
  • Historical information (Input)
  • Organizational process assets (Input) [Process Asset Library (PAL)]
  • Lessons learned (Output)
  • Supporting details (Output)
  • Information requests (Output)
  • Program management plan updates (Output)
  • Program status reports and performance reports (Input & Output)
70. Outputs common to program management process are:
  • Lessons learned,
  • Supporting details and
  • Information requests
71. The five program management process groups are

  1. Initiating Process group: defines and authorizes the program or a project within the program, and produces the program benefits statement for the program
  2. Planning Process group: plans the best alternative course of action to deliver the benefits and scope that the program was undertaken to address
  3. Executing Process group: integrates projects, people and other resources to carry out the program plan and deliver the program’s benefits
  4. Monitoring & Controlling Process group: requires that the program and its component projects be monitored against the benefit delivery expectations and that the progress be regularly measured to identify variances from the program management plan. This process group also coordinates corrective actions to be taken when necessary to achieve program benefits
  5. Closing Process group: formalizes acceptance of a product, service or benefit/result and brings the program or program component (e.g. project) to an orderly end
72. The activities in the program initiation process provide the baseline for the scope and benefits of the projects.

73. The program charter gives the program existence, is the foundation for the program, and contains the justification for the program

74. Program initiation generally calls for “order of magnitude” estimates of scope, effort and cost.
Such estimates are often called feasibility studies or concept development and can be done in the business case

75. Programs are typically chartered and authorized by an organizational executive committee, steering committee or a portfolio management body

76. The key output from the initiating process is the program charter

77. The charter often contains the vision statement that defines the desired organizational end state to follow successful completion of the program, and is used as the vehicle to authorize the program and officially commence planning

78. The key program-level deliverable of planning process is the program management plan, which defines the tactical means by which the program will be carried out

79. The Executing process group involves managing the cost, quality and scheduled plans, often as an integrated plan; and providing status information and change requests to the program Monitoring and Controlling process group through approved change requests, corrective actions and preventive actions

I have shared colored Inputs, Outputs, Tools & Techniques (ITTOs) for all Knowledge Areas in Box.net under http://www.box.net/shared/f7bk0e5psf

80. The Program Integration Management KA includes the processes and activities needed to identify, define, combine, unify and coordinate multiple components within the program as well as coordinate the various processes and program management activities within the Program Management Process Groups

81. The Program Integration Management processes are
  • Initiate Program
  • Develop Program Management Plan
  • Develop Program Infrastructure
  • Direct and Manage Program Execution
  • Manage Program Resources
  • Monitor and Control Program Performance
  • Manage Program Issues and
  • Close Program
82. The Initiate Program process ends with an either approved charter or the decision not to continue. Either decision is documented in the charter and stored for future reference

83. The authority to approve or reject changes in scope or cost within a defined range of tolerances is often delegated to the program manager, while changes identified within a particular component may require action by the program board or steering group

84. The business case and strategic directive are developed external to the Program and prior to the program’s approval

85. Programs are typically chartered and authorized at the organizational executive level, by a steering committee, a portfolio management body, or an external funding organization

86. Program Management Information Systems (PMIS) collect and manage schedules, costs, earned value data, risk information, changes in component status and issues, and other information needed to manage and control the program

87. Program Management Plan integrates and incorporates all program and component plans. It includes the component milestones, benefit deliverables, and component dependencies

88. The Program Management Plan outlines the key elements of program direction and management. It also identifies how decisions should be presented and recorded, and describes how performance reports will be
prepared and distributed

89. Program Transition Plan outlines the steps needed to move the program from a development state to an operational state pending approval that the program has satisfied all requirements and is ready to turn over to the client or into operations

90. Although the program manager is assigned in the Initiate Program process, the core program management and governance team including the PMO, steering committees, governance body members, key consultants and board of advisors are designated as part of establishing the Program Infrastructure.

91. Change Requests are assessed in Direct and Manage Program Execution process and forwarded to the Program Governance process, which serves to authorize the program to implement the change

92. Some Change Requests may come from stakeholders, identification of missing requirements or technical issues or from external sources

93. The analysis of Change Request should identify impacts to

  • Program Finances
  • Program Schedule
  • Program Requirements
  • Program Architecture Baseline
  • Interfaces among Components
  • Documentation and
  • Risk
94. For most programs, the Program Management Office (PMO) is a core part of the program infrastructure. The PMO supports the management and coordination of the program and component work.

95. Program manager keeps the decision log, which documents all major decisions made in managing the program including the background information supporting the decision. Decision logs are significant especially in
the long-term programs where it may be necessary to look up, sometimes years later, why a particular technical or management decision was made

96. Issues are resolved either through acceptance (where no action is taken) or through changes to the program’s plan. The log of resolved issues should be included in the impact reports and checklists and stored for future references by all stakeholders on an ongoing basis. These assets may also be used to support ongoing and post-program audit inquiries.

97. Program Issues Register log is also used in Program Risk Management as an input for the incidental and ongoing management of risk

98. Monitoring is performed throughout a program’s life cycle, which includes collecting, measuring and disseminating performance information, and assessing overall program trends

99. Requests for corrective or preventive action are taken to Program Governance for approval

100. Program Performance Analysis include
  • Gap Analysis
  • Risk Analysis
  • Issues Analysis and
  • Trend and Probability Analysis

101. Projects under the program needs to be closed before the program is closed

102. As each project or non-project activity closes, program closure should be done to capture information and records, archive them, communicate the closure event and status, and obtain sponsor or customer sign-off

103. Efficient and appropriate release of program resources is an essential activity of program closure. At the component level, Program Governance releases resources through the Approve Component Transition process

104. The program itself is formally closed out by either cancelling the program, delivering the program to the customer, or by transitioning the program into operations

105. Before the program is closed, all components should be successfully completed and all contracts formally closed


106. Product Scope – The features and functions that characterize a product, service or result

107. Project Scope – The work that needs to be accomplished to deliver a product, service or result with the specified features and functions

108. Program Scope – The work required to deliver a major product, service or benefit result with the specified features and functions at the program level

109. The Program Scope Management Plan helps the program manager establish the scope statement and requirements, create the PWBS, validate that the deliverables and work of the program were built correctly, and address scope- related changes to the program and its projects

110. As one plans for the scope of the program, following documents best describe as what must be analyzed
  • Program Charter and
  • Business Case
Which are inputs to Plan Program Scope

111. The Program Scope Statement describes the scope, limitations, expectations, and the business impact of the program as well as a description of each project and its resources. It is the responsibility of Program Manager

112. The Scope Statement should address the following topics
• Organizational needs and requirements
• Initial, high level product requirements,
• Vision of the solution and
• Assumptions and constraints

113. A Focus Group is a group of individuals assembled to address specific questions about their attitude towards a product, service or concept. These questions are asked in an interactive group setting where participants are free to talk with other group members. Focus groups may solve problems and/or find solutions to the case in hand

114. The Benefits Realization Plan identifies the business benefits and documents the plan for realizing the benefits

115. Additionally the Benefits Realization Plan identifies the organizational processes and systems needed for the transformation, the required changes to the processes and systems, and how and when the transition to the new arrangements will occur

116. The benefit realization plan is created to
  • Memorialize the proposed benefits of the program for team monitoring,
  • Distinguish the processes and systems needed to achieve the benefits,
  • Detail the manner in which the benefits will be achieved, and
  • Develop the schedule for transitioning the benefits
117. Developing the Program WBS (PWBS) is the process of subdividing the major program deliverables, project activities, and implementation phases of the program. It is the process of breaking down all the work activities into more manageable components

118. A PWBS is a deliverable-oriented hierarchical decomposition encompassing the total scope of the program, and it includes the deliverables to be produced by the constituent components

119. The inputs to Develop Program WBS are
  • The program architecture baseline,
  • Program requirements document, and
  • component requirements documents
120. Elements not in the PWBS are outside the scope of the program

121. The PWBS is a key to effective control and communication between the program manager and the managers of component projects

122. The PWBS components at the lowest level of the PWBS are known as Program Packages


123. The complete description of the PWBS components and any additional relevant information is documented in the PWBS Dictionary, which is integral part of the PWBS

124. The PWBS does not replace the WBS required of each project within the program. Instead, it is used to clarify the scope of the program, help identify logical groupings of work for components, identify the interface with operations or products, and clarify the program’s conclusion.

125. The PWBS (program work breakdown structure) is generally created by
  • The program manager,
  • The program management team,
  • The project managers, and
  • The team doing the work
126.Once the PWBS (program work breakdown structure) is created, you can begin to create
  • Schedule,
  • Budget,
  • Assignment of resources, and
  • Risk planning

127. In creating the PWBS (program work breakdown structure), you must apply the 100% rule: 100% of the work needs to be represented in the PWBS

128. The purpose of the Work Breakdown Structure Matrix is to organize and categorize work scope

129. The Program Architecture is the starting point for developing the PWBS as it contains the necessary elements

130. As the program management team begins to plan the program architecture, it will refer to “Program requirements document” as a reference because it depicts requirements that deliver benefits and addresses enterprise, environmental, legal, and technical consequences.

131. Large, complex projects are organized and understood by breaking them into progressively smaller pieces until they are a collection of defined “work package” that may be further broken down into tasks

132. The Task Responsibility Matrix is a tool to help document and communicate the roles and level of involvement each team member and/or different functional groups will exercise in the ownership of specific tasks

133. The task responsibility matrix is an array of roles and involvement levels for each team member

134. System Configuration tools provide consistent documentation of product versions for use throughout the program. These tools help to provide change control for design documents, scope, requirements, processes and the myriad of items that will be modified during the life of the program

135. The change control process on a program is often hierarchical. The program has a change control board (CCB) that analyzes changes at the program level. If the program CCB identifies an impact to a component, the change is sent to the component-level CCB for a more detailed impact analysis. The results of that analysis are returned to the program CCB and any impacts to other components or to component interfaces are identified


136. The initial Program Schedule is often created before the detailed schedules of the individual components are available

137. The schedule at program level should include only those component milestones that represent an output to the program or share an interdependency with other components

138. A Program Schedule is typically created using the program work breakdown structure (PWBS) as the starting point. It includes all the program packages’ in the PWBS that produce the deliverables

139. A program tool used in developing the program schedule is schedule management software

140. Benefits Analysis is the process of looking at any incremental benefits the program provides and making adjustments to the schedule to enhance the delivery of those benefits

141. Cash Flow Analysis examines the funding schedule for the program’s revenue and expenses

142. Program Master Schedule is the top level program document, which defines the individual component schedule and dependencies between program components (individual projects and other work) to achieve the program goal

143. Earned Value Management is an approach that integrates scope, schedule, and resources to provide an accurate and objective measurement of program and component status

144. Cost Variance = Earned Value – Actual Value

145. Schedule Variance = Earned Value – Planned Value

146. A schedule performance index (SPI) of 0.76 means you are only progressing at 76 percent of the rate originally planned

147. A cost performance index (CPI) of 0.89 means the project is only getting 89 cents out of every dollar invested

148. A manufacturing project has a schedule performance index (SPI) of 0.89 and a cost performance index (CPI) of 0.91. Generally, what is the best explanation for why this occurred
Answer: A critical path activity took longer and needed more labor hours to complete

149. A CPI of greater than one indicates you are taking less money than planed to do the project

150. You are working on a project to build a bridge. You have reached the planned half way mark. The total planned cost at this stage is five hundred dollars. The actual physical work that has been completed at this stage is worth $400. You have already spent one thousand dollars on the project. What is the CPI?
CPI = EV/AC = 0.4
EV=400, AC = 1000, PV=500


151. The Program Charter is the key input to the Program Communications Process. It helps determine the communications requirements by providing information about the Program’s requirements, business needs, purpose, as well as other high-level information.

152. Stakeholder Register is a critical input to Program Communications Planning as it provides a description of the stakeholders and helps guide decisions about the best ways to communicate with the various stakeholders to ensure optimal exchange of information

153. The power/interest grid graphically illustrates which stakeholders need to be kept satisfied, managed closely, monitored, or kept informed based on the level of their power and their interest in the outcome of the project

154. The Program Master Schedule outlines the individual component schedules and dependencies between program components including individual projects and other work. The Program Master Schedule determines the timing of individual component milestones

155. Communications Log includes comprehensive log of stakeholder meetings and communications, which is maintained by Program Manager or Program Communications Leader. The log should identify the who, what, when, how and why for each form of communication

156. Common formats for performance reports include
• Bar Charts
• S-Curves
• Histograms and
• Tables

157. Program Risk is an event, or series of events or conditions that, if they occur, may affect the success criteria of the program

158. Program Risks categories include
• Environment – level Risks
• Program – level Risks
• Project Risks
• Operational – level Risks
• Portfolio – related Risks
• Benefits – related Risks

159. Program Architecture Baseline is a plan that describes where the Program will be at a given point in time, how it will get there, and how to determine if it was successful

160. The program architecture baseline is comprised of the components that provide the specified benefits of the program and delineates their attributes, skills, timing and external interactions

161. Breakdown structures used in program and project management could include
  • Organizational breakdown structure,
  • Risk breakdown structure,
  • Resource breakdown structure, and
  • Bill of materials
162. The organizational breakdown structure is used to show reporting relationships

163. The risk breakdown structure is used to decompose risk on a program or project

164. The resource breakdown structure is used to show what work the resources are doing and

165. The bill of materials shows assemblies, sub-assemblies, etc. of what is being created

166. Risk reviews verify that the risks are still valid and that no new risks have appeared on the project

167. Risk Breakdown Structure is a hierarchically organized depiction of causes of program risks arranged by risk category and subcategory

168. Tools & Techniques for Identify Program Risks Process includes
• Documentation Reviews
• Information Gathering Techniques
a. Brainstorming
b. Delphi Technique
c. Interviewing (Internal & External)
d. Root Cause Identification
e. Business Case Analysis
• Checklist Analysis
• Assumption Analysis
• Diagramming Techniques
a. Cause – and –effect diagrams
b. Program dependency analysis
c. Influence diagrams
d. Affinity diagrams
• SWOT Analysis
• Lessons Learned Review
• Scenario Analysis

169. The Four Factors which the Program Management Team and Risk Managers must continually be aware of, and manage are
• Availability of information
• Availability of resources
• Time and cost and
• Control

170. Make-or-Buy Analysis is a technique that is performed at the beginning of the Plan Program Procurement process

171. Bidder Conferences (also known as contractor conferences, vendor conferences, pre-bid conferences) are meetings with prospective sellers prior to preparation of a bid or proposal. The objective is to ensure that all
prospective sellers have a clear and common understanding of the procurement.

172. A Contract is a mutually binding agreement that obligates the seller to provide the specified products, services or results and obligates the buyer to provide monetary or other valuable consideration

173. A procurement audit confirms whether the seller delivered on its contractual obligations and that the statement of work and its components were achieved

174. Program Business Case is developed before the program is approved. It is obtained from the client, the funding organization or from the program sponsor

175. The Program Manager uses the Stakeholder Register to ensure that no stakeholders are overlooked

176. Stakeholder Inventory contains a current log of impacts identified during stakeholder analyzes, issues raised by stakeholders during engagements and tracking of impact mitigation and issue resolution status

177. The stakeholder inventory includes
  • A recap of the effect of the program has on each stakeholder/stakeholder group,
  • An analysis of probable responses by stakeholders,
  • Stakeholder issues, and
  • Proposed methods of lessening the negative impact of those issues;
some component stakeholder issues are addressed at the program level

178. Program Governance is a practice of developing, communicating, implementing, and monitoring policies, procedures, organization structure, and acts associated with the program.

179. Program governance provides the following:
  • A framework for efficient and effective decision making
  • A consistent delivery management focused on achieving program goals
  • An appropriate mechanism to address risks and stakeholder requirements
180. Program governance should fit into corporate governance, and into the big picture of the organization. The big picture is formed by the three key concepts: mission, vision, and strategy, as described in the following:

Mission: The mission of an organization is a summary of its goals and objectives. It is what an organization does: the purpose for the organization to exist. The mission is expressed in the mission statement, such as the following: “Our mission is to level the playing field in education by providing affordable and quality education to low- income families.”

Vision: This refers to a description, in graphic terms, of where the goal setters want to see the organization in the future. Unlike a mission statement, which is true in the present, the vision statement points to
the truth in the future. Here is an example of a vision statement: “Our goal is to become the number-one education provider in the world.”

Strategy: This refers to a long-term plan of action designed to achieve the organization’s goals and objectives; that is, its mission and vision

181. The term governance refers to procedures, processes, and systems used by an organization (or society) to operate. The word governance has a Latin origin that means to steer

182. Program Governance activities are conducted through all phases of the Program Life Cycle and relies on a governance framework that can be used across the program

183. Just like Quality cannot be inspected into a product, governance must be pro-active and not performed afterwards

184. Program Governance structure is fulfilled through the common roles
• Executive Sponsor
• Program Board (Steering Committee)
• Program Manager
• Project Managers
• Program Management Office (PMO)
• Project Teams and Team Members

185. The following sub plans of the overall program management plan are essential inputs to the Program Governance process
• Program Charter
• Program Business Case and
• Sponsor and Stakeholder Requirements

186. Cost of Quality refers to the total cost of all efforts to achieve product or service quality and includes all work to ensure conformance to requirements, as well as all work resulting from nonconformance to requirements

187. There are three types of costs that are incurred
• Prevention Costs
• Appraisal Costs and
• Failure Costs
a. Internal Costs
b. External Costs

188. Governance is defined as the process of developing, communicating, implementing, monitoring and assuring the policies, procedures, organizational structures and practices associated with a given program

189. Governance is oversight and control. Status report, financial report & resource deviation report are examples of reports submitted to the governance board to support its role of oversight and control

190. Governance plan includes
  • Addressing objectives,
  • Framework,
  • Function and accountability,
  • Planning and meetings,
  • Component initiation,
  • Escalation, and
  • The conduct required to effectively execute the program, and also addresses Monitoring and controlling
191. The component transition decision, benefits realization report updates, lessons learned, and program management plan updates are the results of the Approve Component Transition process

192. Project Quality is defined as the degree to which a project satisfies its objectives and requirements

193. Managing by Leadership is overall more effective and productive than Managing by Authority

194. A benefit is a positive contribution or improvement to the running of an Organization, such as increased revenues, reduced costs and improved employee morale. Can be classified broadly as
• Tangible: Quantifiable benefit, which may be directly related to the financial objectives, such as a 10% increase in revenue
• Intangible: Not easy to quantify, such as improved employee morale or increased customer satisfaction. However intangible benefits can contribute to tangible ones

195. Because programs are run to realize benefits, benefits management starts before the program is initiated, runs through the program and lasts until after the program is closed

196. Balanced Scorecard: According to the Balanced Scorecard technique, developed by Robert Kaplan & David Norton, strategic goals are partitioned into four dimensions:
• Customer (How do our customers see us)
• Financial (What financial gains we obtain through our investment)
• Internal Operations (What is our Core Competency) and
• Learning & Innovation (How do we continue to improve and create value)

197. As the program progresses, the list of stakeholders and their interest may vary. Therefore, program stakeholder analysis should be an ongoing iterative activity (not just a one-time task) whose results can be used throughout the life cycle of the program

198. Key performance indicators (KPIs) are the metrics used to measure performance at different levels, such as strategic plan, program, and project levels. Some KPIs can be used only at one level, and others can be used at more than one level. The KPIs at the strategic-plan level are typically used to quantify business objectives in order to measure the strategic performance of an organization. KPIs at the strategic-plan level are used to accomplish the following:
• Assess the current state of the organization’s business and recommend appropriate actions
• Monitor the business activity in real time.
• Measure activities that are otherwise difficult to measure, such as customer satisfaction and benefits from employees’ skill development

199. KPIs need to be SMART—specific, measurable, achievable, realistic, and timely:

200. A program may include elements of the work related to the program, e.g. ongoing operations, which are outside the scope of all individual projects included in the program.

201. Ongoing and repetitive streams of operations in an organization are neither projects nor programs, according to the standard definitions of a project and a program

202. Earning before interest and taxes (EBIT) is the metric, which refers to an organization’s earning, and is also called operating income

203. The rationale used for launching a program rather than a set of projects can include the following:
• In a program, you can make optimal use of resources (e.g., share them) across multiple constituent projects in the program.
• When the interrelated projects are being managed as a program, you can make optimal resolution and use of dependencies among them.
• A program allows you to coordinate the participation in constituent projects from across different departments in the organization to improve efficiency and performance.
• Programs are more strategic than projects, and therefore they help keep the projects properly aligned to realize the strategic benefits for which the program (and the projects) is being performed

204. The high-level business plan for the program must reflect that the strategic initiative acting as a stimulus for the program is clearly understood. It should align the program objectives with the strategic objectives for which the program is being proposed. It should clearly state the following components:

• Mission: The mission states what the program will achieve and
why that achievement is important.

• Vision: The vision shows how the end state resulting from the
program looks and how the organization will benefit from it. In
other words, it states where the program will take the
organization.

• Values: This refers to what’s important to the program; that is,
how the program will evaluate necessary tradeoffs to strike a
balance between different options


205. A milestone is a significant point (or event) in the life of a program, marking the start or completion of an activity or a set of activities, and therefore has zero duration

206. A gap analysis is performed to ensure that the program deliverables and objectives are aligned with the organization’s strategic objectives. To be specific, the gap analysis begins with asking if there is any potential gap between:
• Program deliverables and program requirements
• Program benefits and program requirements
• Program deliverables and the appropriate parts of the strategic plan
• Program benefits and the appropriate parts of the strategic plan

207. Benefit-cost ratio (BCR): This is the value obtained by dividing the benefit by the cost.

208. The greater the value, the more attractive the project is.
For example, if the projected cost of producing a product is $20,000 and you expect to sell it for $60,000, then the BCR is equal to $60,000 ÷ $20,000 = 3

209. For the benefit to exceed the cost, the BCR must be greater than 1

210. Cash flow (CF): While cash refers to money, cash flow refers to both the money coming in and the money going out of an organization. Positive cash flow means more money coming in than going out

211. Cash inflow is a benefit (income) and cash outflow is a cost (expenses)

212. Discounted cash flow (DCF): The discounted cash flow refers to the amount that someone is willing to pay today in anticipation of receiving the cash flow in the future. DCF is calculated by taking the amount that you anticipate to receive in the future and discounting (converting) it back to today on the time scale. This conversion factors in the interest rate and opportunity cost between now (when you are spending cash) and the time when you will receive the cash back

213. Internal return rate (IRR): This is an investment analysis method used to decide if a long term investment should be made. The investment of capital in a project is a good investment proposition if its IRR is greater than the rate of interest that could be earned by alternative investments, such as investing in other projects, buying bonds, or depositing the money in a bank account. This is just another way of interpreting the benefit from the project. It looks at the cost of the project as the capital investment and translates the profit into the
interest rate over the life of that investment

214. The bigger the IRR value, the more beneficial the project or program is

215. Present value (PV) and net present value (NPV): To understand these two concepts, understand that one dollar today can buy you more than what one dollar next year can buy (think of inflation and return). The issue arises because it takes time to complete a project, and even when a project is completed its benefits are reaped over a period rather than immediately. In other words, the project is costing you today but will benefit you tomorrow. So to make an accurate calculation of the profit, the cost and benefits must be converted to the same point in time.
The PV is the present value of a future payment; that is, a future amount converted into the present time by taking into account the time value, such as predicted inflation and interest.

216. The NPV of a project is the present value of the future cash inflows (benefits) minus the present value of the current and future cash outflows (cost).

217. For a project to be worth while economically, the NPV must be positive

218. Opportunity cost: This refers to selecting one project instead of another due to the scarcity of resources. In other words, by spending a dollar on this project we are passing on the opportunity to spend that dollar on another project.

219. The smaller the opportunity cost, the better it is

220. Return on investment (ROI): The ROI is the percentage profit (or loss) from the investment in a project.
For example, if you spend $400,000 on a project and the benefit for
the first year is $500,000, then ROI = ($500,000 – $400,000) ÷ $200,000 = 50 percent

221. To exceed the cost, the BCR must be greater than 1

222. The constrained optimization methods employ complex mathematical models that use formulae and algorithms to predict the success of a project. These models use the following kinds of algorithms:
  • Linear
  • Nonlinear
  • Dynamic
  • Integer
  • Multiple objective programming
223. Assumptions can appear in both the input and the output of various processes

224. Organizational process assets are also called a process asset library (PAL)

225. The Organizational Process Assets (also called the Process Assets Library) will provide
  • Process definitions,
  • Process documentation,
  • Templates,
  • Closing criteria,
  • Issue management,
  • Knowledge bases,
  • Historical information and
  • Lessons learned
226. Organizational process assets can be inputs to many processes since they deal with variables external to the project. Variable examples are
  • Information systems,
  • Company policies, and
  • Company procedures.
The assets can include
  • Process definitions,
  • Documentation associated with the processes,
  • Templates,
  • Criteria to complete (close) projects,
  • Organization communication needs,
  • Issue management,
  • Financial infrastructure,
  • Change control processes,
  • Risk management,
  • Knowledge bases (including lessons learned),
  • Other information repositories, and
  • Work authorization.

227. An important task of resource planning is to ensure the optimal use of resources across the multiple projects within a program, which is accomplished by using optimization techniques.

228. One such
optimization technique is called load balancing

229. Decomposition is a technique for subdividing the program deliverables into smaller, manageable tasks called program packages. A program package is a bottom component of a branch of the PWBS hierarchy

230. A work package corresponding to an individual project in the program is further decomposed into more levels of hierarchy, with the lowest level containing what are called work packages for the project.

231. The hierarchical structure that contains work packages at the lowest level of each of its branches is called a work breakdown structure (WBS)

232. The program scope statement describes the scope of the program in detail, whereas the PWBS presents the deliverable-oriented decomposition of the program scope

233. Transition planning ensures that the benefits the program provides to the organization are sustained after the program completion

234. The transition does not have to wait until the completion of the program. The transition events can happen when necessary during the program life cycle, such as when a project or a non-project work activity within the program is completed

235. Lateral thinking: Thinking outside the box, beyond the realm of your experience, to search for new solutions and methods rather than only better uses for the current solutions and methods.

236. Resource leveling is a project management process used to examine unbalanced use of resources (usually people or equipments) over time, and for resolving over-allocations or conflicts.

237. There will be elements in the PWBS for which your organization lacks the resources. You will need to get those elements produced by resources (a vendor) external to your organization. This practice is called procurement

238. Both internal and external dependencies can be grouped further into mandatory dependencies and discretionary dependencies, discussed in the following:
• Mandatory dependencies: These are the dependencies that are inherent to the program components. For example, a course must be developed before it can be tested.
• Discretionary dependencies: These are the dependencies that are at the discretion of the program management team. For example, it was possible to perform components A and B simultaneously or to perform A after B was finished, but the team decided, for whatever reason, to perform B after A is finished. Some of the guidelines for establishing discretionary dependencies can come from the knowledge of best practices within the given application area, and from the previous experience of performing a similar program

239. Mandatory dependencies are called hard logic, whereas discretionary dependencies are called soft logic

240. The external dependency is a dependency that is outside the control of the internal organization.

241. The mandatory dependency is required, but internal to the organization.

242. You create the PWBS and WBS and decompose the program packages with the help of the program team and project managers. When decomposing a work package into activities, involve the individuals who either are familiar with the work packages or will be responsible for them

243. Analogous estimating: Analogous estimating techniques estimate the duration of an activity based on the duration of a similar activity in a previous program or in another project.

244. Parametric estimating: This is a quantitative technique used to calculate the activity duration when the productivity rate of the resource performing the activity is available. You use a formula such as the following to calculate the duration:

245. Activity duration = units of work in the activity ÷ productivity rate of the resources

246. Reserve analysis is used to incorporate a time cushion into your schedule; this cushion is called a contingency reserve , a time reserve , or a time buffer

247. The milestones in a program may correspond to key deliverables within the constituent projects of the program

248. Cost aggregation is the technique used to calculate the cost of a whole by summing up the costs of the parts that comprise the whole.

249. Bottom-up estimation uses cost aggregation. You can aggregate the costs of all the program components to calculate the total cost of the program

250. Control thresholds: This refers to the tolerance of the organization to the variations in the cost with respect to the planned cost and budget. If the cost exceeds this threshold, it is called out of control

251. Precision level: This refers to how precise the cost estimates are. For example, it may specify the precision level to which the estimation number will be rounded off—e.g., $100 or $1,000

252. At the precision level of $100, an estimate of $3,675 is reported as $3,700, whereas in the precision level $1,000, it will be reported as $4,000.

253. Units of measurements: This refers to the units of measurements for the resources—for example, work in hours and cost in U.S. dollars.

254. Resource leveling and resource optimization are not identical. Even if a plan has used resource leveling—that is, no resource is over-allocated—it does not necessarily mean that the resources are being used optimally.

255. Bids and quotations are typically used to ask for prices, whereas proposals are used to ask for solutions

256. Invitations for bid, requests for quotation, and requests for proposal travel from buyer to seller, whereas bids, quotations, and proposals travel from seller to buyer

257. Fixed-price (lump-sum) contracts: A fixed-price contract, also called a lump- sum contract or a firm fixed-price contract, is an agreement that specifies the fixed total price for the product, service, or result to be procured.

258. An example of a fixed-price contract is a purchase order for the specified item to be delivered by a specified date for a specified price. This category of contracts is generally used for products and services that are well-defined and have good historical information. A fixed price for a poorly defined product or a service with very little historical record is a source of high risk for both the seller and the buyer

259. Both fixed-price contracts and cost-reimbursable contracts can include incentives; for example, a bonus from the buyer to the seller if the seller meets certain target schedule dates or exceeds some other predetermined expectations

260. Crashing: A schedule-compression technique used to decrease the project duration with minimum additional cost. A number of alternatives are analyzed, including the assignment of additional resources.

261. Critical path: The longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project.

262. Fast-tracking: A schedule-compression technique used to decrease the project duration by performing project phases or some schedule activities within a phase simultaneously when they would normally be performed in sequence.

263. Float time: The positive difference between the late start date and the early start date of a schedule activity.

264. Free float (FF): The maximum amount of time by which a given activity can be delayed without delaying the early start of any of the immediately following scheduling activities

265. Total float (TF): The maximum time by which a given activity can be delayed from its early start date without delaying the finish date of the project

266. Program quality: is a measure of the degree to which the completed program objectives and deliverables meet the program requirements

267. Risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on meeting the objectives of a program or its constituent projects

268. A document that contains the list of all risks with information about each risk, such as priority and a response plan, is called the risk register

269. The goal of risk response planning is not to eliminate all the risks; it is to maximize the opportunities offered by the positive risks and minimize the threats posed by the negative risks

270. Residual risk: A risk that remains after the risk response has been performed

271. A quality audit is a structured and independent review to determine whether the execution of a program or one of its components complies with the policies, processes, and procedures of the program and the performing
organization

272. Generally speaking, differences of opinion should not be considered as sources of conflict. If managed properly, differences can be very healthy and can lead to better solutions and therefore increase productivity.

273. A schedule variance does not necessarily mean that a schedule change is required. For example, a delay on a schedule activity that is not on the critical path might not trigger any schedule change.

274. Pareto's Law, in its original form, was presented as an economic theory by Vilfredo Pareto, a 19th-century Italian economist, and it states that 80 percent of income is earned by 20 percent of the population. Since then it has been applied to other fields, such as project and program management

275. Because closing the constituent projects is included in the program closure, the program closure activities are performed throughout the program, not just at the program completion

276. If a contract has been terminated before its full implementation, it still needs to be closed by using the Contract Closure process.

277. A program is closed by using the Close Program process. Before you can complete closing a program, you must close all the program components and the program contracts

278. Lessons learned are created during the program closure. Lessons learned are considered and input and an output of program closure, because this documentation is cumulative through the program

279. The sequence for program closure is:
  • Perform close program and approve component transition activities,
  • Deliver required reports associated with closing the project,
  • Deliver required reports associated with closing the program,
  • Close out any contracts applicable to the project,
  • Perform final lessons learned for the project,
  • Archive project files (including contracts),
  • Release project resources and assets.
When these activities are complete for all projects (components), the following
activities need to be done:
  • Final closing of the program,
  • applicable administrative activities,
  • Create final lessons learned for the program,
  • Complete program file archives (including contracts), and
  • Release resources and assets back to the company

280. Program files are documents that record what occurred, what decisions that were made, and what changes were approved, including financial records, and legal documents

281. Stakeholder analysis chart identifies the stakeholders, their position regarding the program, what influence they have over the program decisions, and their priorities for the program.

282. Stakeholder analysis is the identification of stakeholder needs, wants and expectations. It involves the documentation, prioritization and the quantification of the needs to help define the project scope.

283. The resource breakdown structure is a chart that identifies needed resources based on the decomposition of the program or project scope

284. RACI chart is a roles and responsibilities chart typically used for team members assignments. This chart uses the legend of responsible, accountable, consult, and inform for each assignment

285. The RACI matrix (pronounced /reisi/..Race ending with an ee) is a formal way of establishing the role for each stakeholder/participant whenever multiple parties are involved In a nutshell:
R(esponsible) – Who is responsible for actually doing it?
A(ccountable) – Who has authority to approve or disapprove it?
C(onsulted) – Who has needed input about the task?
I(Informed, kept) – Who needs to be kept informed about the task?

286. Preventive action: anticipate problems and then creates a solution before the project may begin

287. Corrective action: is a response to fix a problem that has occurred in the program or project

288. Quality assurance: does establish the quality expectations of the program, provide a method to achieve the expected quality, and aims to plan quality into the program.

289. Quality assurance is a management-driven process that plans how quality will be achieved

290. Team development: is a team activity that brings team closer together as a unit.

291. The certificate of program closure is the document that officially closes the program

292. The certificate of program closure includes details of the program’s deliverables, successes and failures of the of the program’s project, and is issued after completion of a program

293. During program initiation following are identified
  • Program scope
  • Program benefits
  • Link to organizational strategy

294. Program risks are NOT identified during program initiation. Program risk is identified as part of the organization’s portfolio management

295. Quality Assurance is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements. It is a prevention-driven activity to reduce errors in the project and to help the project meet its requirements. It is a prevention-driven process that aims to do the work correctly the first time

296. Quality control is an inspection-driven process that examines the work to ensure that it has been done properly

297. Interface Management Plan should define all the people, groups, and other entities that the program needs to interact with in order to move the program forward (SPM V1)

298. Risk avoidance is the elimination of a risk or threat, usually by eliminating the cause.

299. transference is the allocating of responsibility for and impact of the risk event to another party.

300. Risk mitigation is the minimizing of a risk event by minimizing the likelihood of its occurrence.

301. Risk acceptance is the acceptance of the impact or consequences of a risk event

302. The Ishikawa diagram (fishbone diagrams or cause-and-effect) is useful for isolating the area or areas that could be causing the problem with the manufacturing process.

303. The Pareto diagram is useful for determining the type and quantity of defects that exist in the process.

304. The flowchart is a diagram that displays the connectivity between pieces of a system.

305. The control or run chart is useful for determining the measured output over the manufacturing process for acceptable and failed products

306. The program office provides administrative support to program managers and program management teams.

307. The program governance board is responsible for achieving program goals. This also includes supporting program risks and issues.

308. The program director is the executive owner of the program.

309. Governmental regulatory agencies have external regulatory authority that can create new policies which may impact the company and the program

310. Configuration management is a process that is used to control product features and details through change control

311. Interviews are a focused questioned approach with either open or close ended answers.

312. Brainstorming is an approach that allows a free flowing of ideas to document potential solutions to a problem or situation.

313. Questionnaires and surveys are often used to determine people’s reactions to products or approaches.

314. Conflict management is performed to harmonize the varying goals of the stakeholders

315. The Program management plan is a key input of Manage Program Issues

316. Change requests are included in the key outputs of Manage Program Issues

317. A work authorization system helps to ensure that work is done as planned. The right work, in the right order, by the right people. It can be used to minimize gold plating. It is associated with the Direct and Manage Program Execution process

318. In managing program resources, following inputs are needed
  • Program management plan,
  • Component status reports,
  • Resource availability, and
  • Program resource plan
319. During the direct and manage program execution process following must be considered
  • Program management plan,
  • Program roadmap,
  • Change requests,
  • Audit reports, and
  • Program performance reports
320. During the initiating program process following must be considered
  • Business case,
  • Strategic directive,
  • Existing components, and
  • Existing organization structures and policies
321. During the develop program management plan process following must be considered
  • Program charter,
  • Program roadmap, and
  • Existing organizational work
322. During the Control Program Performance process following must be considered
  • Program management plan and
  • Program performance reports
323. The purpose of the transition plan is to address the transfer of component and program work or benefits into organizational operations

324. Manage Program Resources is impacted at the project level by
  • Manage Project Team,
  • Verify Scope, and
  • Report Performance
325. The Project Management Information System (PMIS) is used for communication and information distribution on the program or project. Typically, it is a mixture of technology and non-technology tools used by various people in the project or program

326. Earned value reporting shows the status of the scope, time, and cost of the project.

327. Fixed formula progress reporting uses a partial credit approach (e.g. 50/50) and is ideal when the duration of an activity is equal to or less than two reporting periods.

328. The weighted milestone approach is ideal when the duration of an activity is more than two reporting periods.

329. Forecast reporting focuses on future activities of the project

330. The inputs to the Report Program Performance process are
  • Program performance reports,
  • Program forecasts,
  • Communications messages, and
  • Benefits realization plan

331. The para-lingual communication process includes voice characteristic analysis Variance reports show the difference between what was planned and what actually occurred.

332. Forecast reports provide information on what is expected to occur.

333. Progress reports provide information on what has been accomplished recently.

334. Status reports provide information on the present overall state of the project.

335. Informal written includes non-legal documents, documentation that precedes any contracts, general documentation, and notes.

336. Formal written is used when distance or extreme complexity is involved, for legal communication, and for program and project documents.

337. Formal verbal communication is used in official situations, presentations, and other communication that is primarily one-directional.

338. Informal verbal includes any verbal communication that isn’t formal, such as people talking together and it does include meetings

339. The performing organization is the group (company, department, division) that is doing the work of the program and its related projects

340. Pre-program preparations involve starting program efforts.

341. Program initiation involves creating planning documents for the program.

342. Establishing the governance for the components (projects) of the program is an output of delivery of program benefits.

343. Program closure involves shutting down the projects and contracts of the program, and ultimately the program, when the work is complete

344. The activities and deliverables of benefits analysis are create and prioritize projects and establish benefits metrics;

345. The activities and deliverables of benefits identification are determine benefits, evaluate benefits, and rank benefits;

346. The activities and deliverables of benefits planning are create benefits monitoring and the benefits realization plan and align benefits into the program management plan;

347. The activities and deliverables of benefits realization are monitor projects, maintain benefits register, and create benefits reporting

348. Program and projects can both create deliverables, with the main focus of the program being to create incremental benefits via the project deliverables. Projects themselves do not create incremental benefits, those come via the program. Both programs and projects should be run within a governance structure

349. The sponsor funds a component within the portfolio.

350. The Executive Review Board authorizes the scope with which portfolio management directs portfolio operations.

351. The portfolio manager is responsible for managing a portfolio.

352. The portfolio management board typically establishes the framework, rules, and process for the decision aspects of the portfolio

353. Verification of the benefits of the program comes as a result of scope verification of the project deliverables.

354. A high level plan to address the mission, vision, and values of the program should be created when deciding to do a program.

355. Administer program procurements involves the management of contracts at the program level which can result in adjustments to resource accounting, approved payment requests, contract changes, program records, change requests, communications messages.

356. Plan program procurements involves the analysis of procurement or outsourcing needs and the development of a strategy to address them.

357. Conduct Program Procurements involves the completion of the solicitation needs for the program and its projects.

358. Close program procurements involves closing contracts that relate to the procured work of the program and its projects.

359. A request for information (RFI) is a request for the service provider to provide information about its qualifications.

360. A request for proposal (RFP) is a request for the seller to provide information about the approach it will take to complete the work, the price of the work, and other significant details about the requested work.

361. A request for quote (RFQ) is a request for the seller to provide the price for a commodity

362. The contract management plan helps the program manager and team define the rules for archiving contract documentation, establishing payments for the work of the contract, addressing changes to the contract, validating completion of the contract work, and closing the contract when the work is complete

363. The fixed-price-incentive-fee provides for a fixed price plus an incentive fee if performance goals are met.

364. The cost-plus contract provides for costs plus a negotiated fee.

365. The fixed-price contract provides for a set price. The fixed-price is the most popular because it allows a company to budget for a fixed price

366. A fixed-price-economic-price-adjust contract generally sets a fixed price, but, because of contract length, will adjust year-by-year as a neutral economic indicator moves upward or downward.

367. Close Program Procurements, Close Program, and Approve Component Transition are all closing processes

368. The key inputs to the Plan Program Procurements process are:
  • Market environmental factors,
  • Program budget allocation,
  • Component scope statements, and
  • Program charter
369. Conduct Program Procurements is the process that follows Plan Program Procurements.

370. Administer Program Procurements occurs after Conduct Program Procurements.

371. The projects created within a program, are often at different stages of completion and therefore planning is more likely to be progressively elaborated.

372. Quality Audits are completed by independent reviewers to determine whether project activities comply with organizational and project policies, processes and procedures.

373. Projects are planned in detail to deliver a product/service or result, programs monitor projects and ongoing work and portfolios identify the current state of program/project investments.

374. The program scope statement contains high level deliverables for the program and the program charter links the program to the ongoing work of the organization

375. The key areas included in the program charter are:-
  • Links the program to the ongoing work of the organization
  • Vision statement that defines the desired end state on successful completion of the program
  • Used as the vehicle for authorizing the program
376. Whereas the program scope statement has:-
  • Objectives of the program
  • High level deliverables of the program
  • Organizational needs and requirements
  • Initial high level product requirements
  • Vision of the solutions
  • Assumptions and constraints
377. Confrontational style involves open and direct communication to resolve the problem, Confrontation requires trust between the parties, and sufficient time to work through the issues to a resolution

378. A strategic plan should ensure achieving the mission

379. Earned value techniques to measure the project performance and establishing forecasts based on the measurements

380. Program are executed to deliver program benefits

381. Program Management Plan includes following subsidiary plans
  • Program roadmap
  • Program schedule
  • Program governance plan
  • Governance metrics and critical success factor
  • Benefits realization plan
  • Program stakeholder management plan
  • Program communications management plan
  • Program financial plan
  • Contracts management plan
  • Scope management plan
  • Procurement management plan
  • Quality management plan
  • Program risk response plan
  • Program risk management plan and
  • Schedule management plan
382. To be successful, benefits management must begin when the program is initiated

383. Although benefits management evolves as the program continues through its phases, it should begin when the program is initiated, in the Pre-Program Preparations and Program Initiation phases of the program life cycle

384. The Direct and Manage Program Execution process is involved in
  • Implementing approved change requests,
  • Maintaining decision logs, and
  • Performing impact analysis.
These tasks are done by the program manager, based on his or her scope of authority

385. The program budget baseline is an input to the Monitor and Control Program Financials process. When a change request with significant cost implications is approved, a program budget baseline update should be prepared as an output of the Monitor and Control Program Financials process

386. Too often, after the business case has been approved, the focus turns to the time, cost, and quality of delivery. Establishing a continuous program management approach where the business case is always tied to program performance will ensure that governance is being followed and the program is meeting the organization’s strategic plan goals

387. Program success can be measured using a variety of metrics; ultimately, it is measured against the needs and benefits of the stakeholders

388. Changes affect the various program-level processes. As part of the Monitor and Control Program Scope process, updates to the document repository may be required based on the nature of the change

389. A component transition request is an input to the Approve Component Transition process, and it is required
if a project is terminated before its scheduled completion. A termination decision may be the result of a program
benefits review or a change in the external environment. The transition request is also required for normal project completion

390. After an issue is identified, it should be recorded in the issue register. The next step is to subject it to analysis by a reviewing authority or board. Issue reviews should be conducted regularly

391. The balanced scorecard is a benefits measurement technique that includes a set of performance measures. These measures cover a range of areas that reflect and show a balanced view of organizational performance.

392. Internal rate of return (IRR) and net present value (NPV) are financial analysis techniques

393. Value engineering is a technique used to reduce costs in product development

394. Balanced Scorecards are generally used in business to provide a balanced view of how a business or business unit is performing, rather than just focusing on financials, as financial results are considered “lag” measures. By “lag” we mean that financials only tell the story of something which has happened in the past

395. A balanced scorecard is a measuring tool that clarifies an organization’s vision through measurable goals and outcomes. This enables the vision to drive the projects that take place within the organization, aligns them to the organization’s overarching business strategy, and correlates their outcomes.

396. Value realization and the balanced scoreboard are examples of metrics

397. Value realization means obtaining value from the investment

398. The Develop Program Infrastructure process investigates, assesses, and plans the support structure to enable the program to achieve its goals. It considers the unique challenges and needs of the program and how program components interact. The program’s management and technical infrastructure support the program and its projects as expected benefits are delivered. This infrastructure includes program-specific governance processes and procedures

399. The executive sponsor is the person who has executive ownership of program policies and is responsible for providing program resources and ensuring program success. Program sponsors represent the organization’s executive management, which is responsible for defining the direction of the organization and making the investment decisions necessary to meet strategic goals

400. The program mandate, which is prepared during the Pre-Program Preparations phase, confirms the commitment of organizational resources. It also triggers the Program Initiation phase. Thus commitment of organizational resources for the initial phases of the program is provided before the Initiate Program process begins

401. Component projects of the program are initiated during the Delivery of Program Benefits phase

402. When a contractor refuses to perform according to the terms and conditions of a contract, he or she is in default and is subject to legal action.

403. The organization’s contract closure procedure, a tool and technique in the Close Program Procurements process, outlines the requirements for contract termination, including verification criteria to protect the organization from breach of contract

404. The program life cycle is nonsequential. Throughout the life cycle, components are mobilized as appropriate so that a stream of deliverables focuses on facilitating new operations and benefits

405. As you work as a program manager to identify, track, and close issues, it is important to do so in tandem with Risk management. t is important to carry out the Manage Program Issues process in tandem with program risk management so that unresolved issues do not affect overall program progress, especially because risk assessment is an integral part of issues management and the risk register is an input to the process

406. Your program is beginning to miss key milestones because of delays by your customer, with whom you have a contract. Your goal is to ensure that corrections are made as quickly as possible, so you decide to conduct a contract performance review earlier than planned. During this review, you and the customer realized that there was a deficiency in the contract. Your next step is to prepare a change request

407. A contract performance review is a tool and technique in the Administer Program Procurements process. Change requests or recommended corrective action requests should be raised when the performance problems are the result of a deficiency in a contract

408. Because most scope changes have associated costs, every proposed change requires analysis to determine whether it should be implemented. After the analysis, the program manager makes a decision. The next step is to communicate the decision to the stakeholders involved

409. The Develop Program Schedule process is both a top-down and a bottom-up approach. The program schedule is created with the PWBS as the starting point. Individual project managers then build the details for their specific projects, and these details are then incorporated into the management control points for the program packages of the PWBS. Project schedule information is an input to this process

410. A 360-degree feedback analysis is an excellent mechanism to look broadly at a person’s management, leadership, and interpersonal skills. It can provide an excellent foundation for future development as well as providing key insights by the people that work with her on a daily basis

411. The executive sponsor is the group or person who is responsible for providing project resources and ultimately for ensuring program success.

412. The Approve Component Initiation process includes the processes and decision-making structure for initiating and changing the overall program as well as its components

413. The component charter, program management plan, and component initiation criteria are Inputs to the Approve Component Initiation process

414. The Manage Program Resources process is ongoing throughout the program. As projects are authorized, resources may need to be redeployed. This redeployment is handled by the program manager at the program level. It may require other program process activity if the project managers are unable or unwilling to release the required resources

415. The program scope statement defines
  • The scope of the program as well as the
  • Limitations,
  • Expectations, and
  • Business impact of the program.
It also describes each project and its resources as well as organizational needs and requirements, initial high-level product requirements, and the program’s vision, assumptions, and constraints. This statement helps the program team to perform more detailed program planning

416. The desired outcome of the Program Setup phase is approval to authorize execution of the program management plan

417. During the Program Setup phase, the foundation of the program—a detailed program management plan—is developed. The program manager continually communicates with stakeholders during this phase, and the desired outcome is approval to execute the plan

418. Many organizations set up a program team to participate in initiation or program start-up and then replace team members with permanent staff during the Manage Program Resources process, which tracks and adapts the use of program resources throughout the life cycle

419. Comparative advantage analysis is a tool and technique of the Initiate Program process. A well-developed business case will include a certain level of analysis and comparison against real or imagined alternative efforts. Such comparisons generate substantive debate with respect to the best solution

420. The Distribute Information process involves providing timely and accurate information to program stakeholders in useful formats and using appropriate media. A key input to this process is a stakeholder register, which lists the primary stakeholders of the program, their roles and responsibilities, and their expectations. Use of a stakeholder register helps to ensure that their information needs are identified and can be met

421. During the Program Initiation phase, the program road map is prepared. Among other things, it describes the links between the planned and prioritized work, and it shows how program components are organized. It also provides a chronological representation of the program’s intended direction.

422. Organizational process assets (a process asset library) are key inputs to many program management processes. They may include the organization’s knowledge bases, may exist in paper or electronic format, and may include process-related plans, policies, procedures, and guidelines institutionalized by the organization.

423. The program charter links the program to the organization’s ongoing work. It contains the vision statement that defines the desired organizational end state for successful completion of the program and describes how the program will benefit the organization

424. The purpose of the program transition plan is to ensure that program benefits will be sustained after they are transferred to the organization. As part of the transition, all pertinent documents, training and materials, supporting systems, facilities, and personnel are delivered. These requirements are part of the program’s transition plan

425. The benefits realization plan must be monitored regularly to determine the actual events and changes in plans at both the component and overall program level.

426. One of the major purposes of the Manage Program Issues process is to identify, track, and close issues so that stakeholder expectations are aligned with program activities and results. This alignment can be accomplished by several methods, including Performing program scope analysis

427. It is important that the program manager ensure that stakeholder activities are aligned with the program’s activities and deliverables. Issues may be sent to program risk management, program governance, or program scope management. When issues are sent to program scope management, then it is important to determine the effect that such issues have on the program’s scope

428. The benefits realization plan includes the responsibility for delivery of the intermediate and final program benefits. Benefits management is a continuous process that assesses the value of the program’s benefits as well
as the interdependencies that exist between benefits in the program’s projects. It also assigns responsibility and accountability for benefits realization

429. The vision is part of the charter prepared during the Program Initiation phase.
The high-level plan shows
  • the stimuli that triggered the program,
  • the program objectives, and
  • how the objectives align with the organization
430. A statistical process control (SPC) chart shows how a process is being executed over time. A process is deemed “out of control” when certain measurements exceed tolerance levels thus affecting quality. The Plan
Program Quality process includes preparation of the program quality management plan, which sets, among other things, quality standards for components.

431. Benefits identification corresponds to the Pre-Program Preparations phase. This is the phase in which benefits are identified and qualified.

432. The program architecture baseline is an output of the Develop Program Architecture process and describes the various program components that need to be in place to produce the desired benefits. Given this change in
scope, this baseline requires updates

433. You will need a number of different types of supplies and services to support your program and its component projects. Many different techniques can be used to evaluate proposals that are submitted. All use Expert judgment

434. Proposal evaluation systems are a tool and technique in the Conduct Program Procurements process. Although a number of different approaches can be used, all use expert judgment and evaluation criteria.

435. A program dashboard highlights and briefly describes or illustrates through the use of colors—red (bad), yellow (warning), green (good)—the status of various aspects of the program. It is simple and easy to interpret, making it a useful communication tool at the executive level. Methods to represent status reports are dashboards, memos, and presentations to stakeholders

436. high-level plan to initiate the program is developed in the Pre-Program Preparations phase. It shows how the program will map to and deliver strategic objectives, and how those objectives align with organizational goals

437. Regular quality reviews and project management health checks are best practices to assess performance against expected and desired outcomes. Health checks are also used to gauge whether the program benefits will be realized in the long term. They are less formal than phase-gate reviews, but they are useful to focus on such areas as quality planning to ensure that the overall program is successful

438. Acquisitions and mergers are unplanned events. When they occur, they should trigger a review of existing program plans to see whether updates are required to ensure ongoing usefulness.

439. Phase four in the program life cycle is the Delivery of Program Benefits phase. This is when the work of the program through its projects and other activities begins. At this time, the program management team is responsible for managing the projects in a coordinated and consistent way, and a governance structure is established to monitor and control the projects

440. As a program is closed, benefits management focuses on a number of key initiatives, including ensuring that the benefits delivered are in line with the business case

441. Stakeholders play a critical role in the success of a program or project. As program manager for development of a next-generation motorcycle to be available in 2020, you know it is a best practice to prepare a stakeholder analysis and management plan. This should be done as the program is being initiated

442. Stakeholders are persons who have an interest in or influence over the program. They may be internal or external to the organization, and their expectations must be managed from the beginning to the end of the program. Stakeholder considerations are stated in the program charter, which is developed during Program Initiation and should include an initial strategy to manage them

443. A risk trigger is a sign that a particular risk may occur

444. Because the WBS defines all work in a project and program, this is the best tool to use for integration. The program work breakdown structure (PWBS) typically corresponds to the first one or two levels of the WBS of each component project. As the PWBS is developed, the management planning process is a key tool and technique to use

445. The communications log is an output of the Plan Communications process. It identifies the who, what, when, how, and why for each form of communication. After the communications framework has been developed
and agreed to, the next step is to identify and put into place the components (that is, the processes and technical elements) that will enable the communications to be executed

446. During the Closing processes, it is important to demonstrate that the benefits have been delivered and the scope of work has been fulfilled. If the program is terminated early, then the current state should be documented

447. Corrective action is an output of the Monitoring and Controlling Program Financials process

448. Program operational cost analysis is a tool and technique in the Monitor and Control Program Financials process. It is necessary because costs associated with program management and the infrastructure must be monitored and controlled

449. A key aspect of stakeholder management is to implement successful organizational change. This includes identifying the people who have an interest in or will be affected by the change and ensuring that they are aware of, supportive of, and part of the change process. Generally accepted methods of organizational change should be part of program plans

450. A benefits realization analysis, which typically follows a benefits review, is a tool and technique of the Manage Program Benefits process. It focuses on strategic alignment, value delivery, resource management, risk management, and performance measurement. This scenario would concentrate on the risk management area to focus on risk awareness by senior enterprise officers

451. A successful program manager must have a special blend of knowledge, skills, and competencies. The most important is communication skills to deal with all program stakeholders.

452. During the Report Program Performance process, performance information is collected, measured, and consolidated, and measurements and trends are assessed to generate improvements. Information about how resources are being used to deliver program benefits is consolidated, and the consolidated information is then made available to program stakeholders through the Distribute Information process

453. The primary output of program initiation is the program charter. Among other things, it includes the recommended governance structure to manage, control, and support the program as well as the governance structure for the program’s components.

454. Phase-gate reviews serve numerous purposes and should be held throughout the program. They focus on the phase that was just completed and result in go/no-go decisions. However, these sessions are not a substitute for periodic program performance reviews

455. As an output of the Monitor and Control Program Financials process, the program budget is closed as the program comes to a close, the final financial reports are distributed in accordance with the stakeholder management plan, and any unused funds are returned to the funding organization

456. Upon completion of the program work breakdown structure (PWBS), realistic schedules can be built, cost estimates can be developed, and the program’s work can be organized

457. One of the truest measures of an organization’s intent, direction, and progress is found in its Portfolio

458. The portfolio is where investment decisions are made, resources are allocated, and priorities are identified. Thus, it is one of the truest measures of the organization’s intent. Program components must be aligned with the organization’s strategy to clearly show why they are being undertaken

459. One objective of the Initiate Program process is to Define the program’s scope and benefit strategy

460. The Initiate Program process helps to define the program’s scope and benefits expectations and ensures that the authorization and initiation of the program are linked to the organization’s ongoing work and strategic priorities

461. Although the type of program may influence the life cycle, the primary life-cycle phases and their deliverables are similar.

462. After you analyze the PWBS, scope statement, and product description, you apply make-or-buy decision techniques to determine which of the PWBS elements will be produced using internal resources and which will be obtained from outside suppliers.

463. The program manager leads interdisciplinary teams as well as functional teams. Programs require resources, and the program manager must be able to obtain needed resources from functional organizations. Strong leadership skills are critical to the successful management of multiple program teams
throughout the life cycle.

464. Status reviews of component financial expenditures are a tool and technique in the Monitor and Control Program Financials process. These reviews should be held regularly to ensure compliance with contracts and with the cost and schedule baselines.

465. Most programs, especially large programs of long duration, use a combination of external and internal resources to ensure that benefits are realized. These resources are Defined in the Develop Program Work Breakdown Structure process

466. The program work breakdown structure (PWBS) formalizes the program scope in terms of deliverables and the work that must be done. It also defines the required resources to perform the work, using a task responsibility matrix as a tool and technique

467. In the program governance framework, benefits enablement is the responsibility of the Program manager

468. The program board is responsible for overall program governance. The program management office (PMO) supports the program manager, who has overall responsibility for benefits enablement

469. You have had several issues on your program. For each one, you have analyzed it and assigned it to an owner. Often the issue resolution has resulted in a need to make a decision, communicate that decision to those
affected, and perform additional work beyond that identified in the program work breakdown structure (PWBS). For each issue, your next step is to Issue a change request

470. Change requests are an output of the Manage Program Issues process. The change request, once approved, may then involve another process for further action. At the end of the program, each change request should be analyzed to provide feedback and recommendations for future programs or projects in the
organization

471. One purpose of review by the program’s governance board is to Initiate another project into the program. Reviews by the program’s governance board are an opportunity for senior management to assess program
performance before the program moves to the next phase or before another project is initiated in the program. This process can occur during any program phase except closing. The criteria for approval are defined in the governance plan

472. Impact analysis is a tool and technique in the Monitor and Control Program Changes process, which explores the effect of the proposed changes on the program. It assesses the accuracy of any assumptions and identifies the potential risks and benefits that possible changes may have on the component projects

473. A process for benefits monitoring is established in the benefits realization phase. At this time, the program manager and the team establish the structure in which work will occur as well as the technical infrastructure to
facilitate the work. This includes establishing a framework to monitor and control the projects and to measure program benefits.

474. Program stakeholder management is concerned with how the program will affect stakeholders in areas such as the organization’s culture, local population, current major issues, and resistance or barriers to change.

475. You are managing a program with a long duration for the water management district in your county. You and your program management team need to analyze any environmental or legislative changes during execution that may affect your program. This is a key activity to perform during the Delivery of Program Benefits phase. Environmental changes are critical, because they can affect the program management plan or any anticipated benefits. As a result, they are an area of emphasis in the Delivery of Program Benefits phase;
these changes must be identified and analyzed

476. A SWOT (strengths-weaknesses-opportunities-threats) analysis provides information that is helpful when matching an organization’s resources and capabilities to the competitive environment in which it operates. It is used in feasibility studies as a tool and technique in the Initiate Program process

477. As an output of the Monitor and Control Program Financials process, updates to the program budget baseline are needed when there are significant cost impacts. These updates are communicated to program stakeholders as appropriate

478. The Closing Process Group formalizes acceptance of the products, services, or results that define the program’s successful completion. It is intended to leave in place a legacy of operational benefits sustainment, thus deriving optimal value from the program’s objectives.

479. Each program is expected to deliver certain benefits that may be tangible or intangible. Benefits realization planning is part of the Initiate Program process. The benefits realization plan, which is an output of the Define
Program Goals and Objectives process, defines each benefit and explains how it is to be realized, maps the benefits to the program’s outcomes, provides a way to measure benefits, describes roles and responsibilities, includes a communications plan, and notes transition to ongoing operations and benefits sustainment. It is a key input to the Plan and Establish Program Governance and Plan Program Quality processes

480. The payback period can be determined by dividing the initial fixed investment in the program by the estimated annual net cash inflows

481. You are a program manager for a software services company. You are expected to develop an initial cost and schedule plan for your new program. This is done in the program life cycle as part of the Program Setup phase

482. You are managing a program that includes 15 component projects. The benefits expected from each project should be defined in the Project business case before the project is initiated. Projects are typically initiated and executed in the Delivery of Program Benefits phase. Projects should not be initiated without having a business case that describes the benefits the project will provide

483. There are a number of key components in the benefits realization plan, which is prepared in the Define Program Goals and Objectives process and maintained throughout the program. Two key components are to ensure that the program is managed in a way that satisfies the use of the program’s outputs and to link the outputs to an outcome of the program. Each benefit should be specific, measurable, actual, realistic, and time-based (SMART)

484. A definition and description of program funding flows are contained in the Program financial framework. The program financial framework is a plan to coordinate available funding, including the specific constraints under which it is available and how the money is paid out. It defines and describes program funding flows in a way that ensures that program funds are spent as efficiently as possible

485. The list of deliverables and the success criteria for the program and its products, services, and results must be included in the procurement documentation that is provided to potential suppliers. This list is derived from
an analysis of the Program scope statement. The program scope statement is the basis for future program decisions, and it defines and articulates the scope of the program. It also contains a list of the program’s deliverables and success criteria; these factors require consideration, because they may need to be included in procurement documentation

486. The Plan Program Quality and Plan Program Procurement processes are closely related, because both can benefit from standardizing product specifications and tests and by establishing economies of scale. The quality
improvement plan focuses on ways to increase customer value by analyzing processes to identify waste and non-value added activities. It includes targets for improved performance as well as process metrics

487. In selecting programs, your committee should focus on such factors as
  • Benefits,
  • Business strategies,
  • Internal and external influences, and
  • Program drivers
488. To regularly report on the status of the program’s benefits, the program manager must be able to measure the benefits that have accrued to date and communicate this information to the program sponsor and the program governance board. The metrics and procedures that will be used are stated in the Benefits realization plan

489. The benefits realization plan is drafted early and maintained throughout all phases of the program. During the Manage Program Benefits process, a benefits realization report is prepared. Among other things, this report tracks the benefits realized against the benefits delivered to the organization

490. You are managing a program and have just learned that there was a failure to adhere to a major scope element in the work breakdown structure (WBS) of one of the key projects. This problem means that Changes to the program architecture may be needed. The Manage Program Architecture process ensures that well-structured relationships among the program elements adhere to the governing rules as defined in the architecture

491. Stakeholder management is critical to program management. Effective, ongoing communication with stakeholders is essential. To complement the communications management plan for the program, you should prepare a Communications strategy

492. Qualified seller lists are used when RFPs, RFQs, or requests for information (RFIs) are issued. They can save time in the overall program procurement management process, because they list only known sellers who can provide needed products and services.

493. A number of activities are typically performed before the program is initiated. These activities result in the development of concepts for products and services, scope frameworks, initial requirements, timelines, deliverables, and guidelines regarding acceptable costs. These activities are required to determine the business case for the program and to seek approval from the governance board or comparable body

494. Because a program is responsible for delivering benefits to the organization, the program manager, members of the program team, project managers and team members, and other program stakeholders all have key roles and responsibilities in benefits management. These roles are set forth in the Benefits realization plan

495. A key component of the benefits realization plan, which is prepared in the early phase of the program, is a description of roles and responsibilities for benefits management.

496. In contrast to the project life cycle, which focuses on producing deliverables, the program life cycle manages outcomes and benefits. The program manager, therefore, manages and accrues the program’s corresponding benefits.

497. The Direct and Manage Program Execution process focuses on managing the execution of the program management plan. The primary goal is to deliver the program benefits based on the component projects. Additionally, the program manager ensures that each project aligns with the program’s business case and strategic directives

498. You are a member of your program’s core team and are preparing the program’s cost estimate. You just met with each of the project managers on this program and received individual estimates for their projects based on their work breakdown structure (WBS) work packages. Your next step is to Prepare program and component cost estimates

499. Program and component cost estimates are the outputs of the Estimate Program Costs process. The program cost estimate is typically prepared in stages and becomes more detailed as additional information becomes available

500. The program resource plan is prepared in the Develop Program Infrastructure process. Capacity planning is used to assess needed resources such as staff, information, expertise, funds, facilities, and production capabilities. Limitations in these resources must be addressed if the program is to be successful.

501. Program governance processes and procedures should be structured and implemented such that critical issues will receive appropriate visibility for their potential effects across other portfolios in the organization.

502. Your organization has implemented portfolio management. In terms of the expected benefits of a program, the first step is to Formalize benefits at the portfolio level. The purpose of benefits management is to define and formalize the program’s expected benefits. If a portfolio management system is established, then the benefits are typically formalized at the portfolio level and then delegated to the program for execution

503. Program performance reports are an input to the Provide Program Governance process. Examples of these reports are
  • Status reports,
  • Financial reports, and
  • Resource deviation reports
504. The Scope Management Plan is an output of the Plan Program Scope process. It provides guidance about how the program scope will be defined, documented, verified, managed, and controlled by the program team. It
controls how requests for changes to the scope statement will be processed.

505. The Pre-Program Preparations phase focuses on preparation and navigation through the selection process. One key activity of this phase is to identify the key decision makers or stakeholders and specify their expectations and interests.

506. A benefits review is a tool and technique in the Manage Program Benefits process. These reviews verify that the delivery of program benefits has not been compromised by decisions made during program execution and reassure stakeholders that all is going well with program components.

507. During the life of a program, certain projects end and others start. Procurement planning is ongoing throughout the life cycle, and make-or-buy analysis is iterative; subsequent procurement activities may indicate a need for a different approach, and new projects may need a different approach as the program ensues. A make-or-buy analysis is performed on each potential project in a program.

508. The outputs of the Distribute Information process include program performance reports as well as updates to
  • Lessons learned,
  • The program communication plan, and
  • The communications log.
509. Communication skills are part of overall general management skills and are required by many program managers. They are a tool and technique in the Distribute Information process.

510. Some projects may produce benefits that can be realized immediately, whereas others may deliver capabilities that must be integrated with those of other projects to realize benefits. The program life cycle may be extended as some projects transition and others begin.

511. The program budget allocations are an input to the Plan Program Procurements process. The program budget takes into account all individual component budgets. Where possible, costs can and should be shared across components. It is the responsibility of the program manager to determine the best use of funds when allocating the budget.

512. One of your first tasks as a program manager is to prepare a benefits realization plan. You will base it on the expected benefits as defined in the Program business case. The benefits realization plan is a part of Program
Initiation. Expected benefits are defined in the business case for the program, and the benefits realization plan is based on this information.

513. In addition to linking the program to the ongoing operations of the organization, the program charter defines the program manager’s level of authority and responsibility. Thus, it is an input to the Plan Program
Procurements process.

514. The sponsor and the program manager are appointed as a result of the Program Initiation phase of the program life cycle.

515. Checklists are a tool and technique in the Plan Program Quality process. These checklists can be very helpful in ensuring that items are not missed as well as in reducing the time it takes to develop quality management plans.

516. Your program team identifies several issues that force you to modify program requirements. Some changes are minor, but one issue requires a program scope change. Your next step is to Prepare a change request

517. To ensure that stakeholder expectations are in line with program activities and deliverables as issues are identified, analyzed, and resolved, it may be necessary to change the program scope. The first step is to prepare a change request, which is an output of the Manage Program Issues process

518. It is common to receive numerous requests for program information from both internal and external stakeholders. Many of these requests are an output of program management processes; they should flow to the Distribute Information process, which creates appropriate responses as outputs.

519. Resources—funding, equipment, and people—are limited in all organizations. In selecting a program, it is necessary to consider the total available resources that will be required to successfully implement it

520. The Closing Process Group formalizes acceptance of the program’s Benefits. The purpose of the Closing Process Group is to formalize acceptance of the program’s product, service, or results to bring the program (or program component) to completion. One purpose is to demonstrate and confirm that all program benefits have been delivered.

521. You are Company A’s program manager for the development of an online banking system for your community bank, for which your company will receive $20 million. Because the bank would like to implement this system quickly, it has also contracted with Company B. You must implement your system completely in six months to ensure that you beat Company B’s schedule. At this point, you have an expense estimate of $2.5 million. You will lose $10 million if you cannot deliver the product in six months, but if you can complete it sooner, you will earn an additional $25 million, for a total of $45 million. Your risk management officer performs a risk analysis and tells you that there is a 70 percent chance that the project will be completed ahead of
schedule. Your company has completed similar projects in the past; judging by these experiences, there is a 30 percent chance that your final expenses will increase by $10 million. What is the expected value of your program if it is completed ahead of schedule
You will earn the difference between $20 million plus 70 percent of the additional $25 million and $2.5 million in expenses plus 30 percent of the additional $10 million in expenses, or—
[$20m + (0.7 x $25m)] – [$2.5m + (0.3 x $10m)] =
($20m + $17.5m) – ($2.5m + $3m) =
$37.5m – $5.5m = $32m
Remember that expected value is calculated as probability multiplied by the monetary value of the risk

522. Supplier performance reviews are a tool and technique in the Close Program Procurements process. They may be the last opportunity for recourse to address performance deficiencies with suppliers.

523. The program manager negotiates and finalizes program-wide policies and agreements. Qualified seller lists are a tool and technique in the Conduct Program Procurements process. If available, these lists can facilitate the
procurement process, as procurement documents can be sent to these prospective sellers to gauge interest and to see whether they want to present a proposal or quotation.

524. To report on the status of the program’s benefits to the sponsor and the governance board, the program manager must be able to measure the benefits that have accrued. The benefits are tracked in a Benefits realization report. The benefits realization report is an output of the Manage Program Benefits process. It compares the benefits realization plan against the actual benefits realized

525. Influence is the ability to affect the beliefs, actions, and attitudes of other people and is a tool and technique in the Manage Program Stakeholder Expectations process.

526. Contingency reserves are an input to the Estimate Program Costs process. They are monies (or time) that are set aside to pay for unexpected requirements changes or program environmental factors and to pay for
mitigating the impact of certain risk events.

527. The benefits realization phase tracks to the Delivery of Program Benefits phase, when the major work of the program is under way. This phase ends when the planned benefits are achieved or when the program is terminated for some reason. The benefits register is maintained during this phase

528. As an output of the Identify Program Stakeholders process, the stakeholder inventory provides a complete and comprehensive overview of how the program’s stakeholders will be affected by the program. It also provides an assessment of likely stakeholder responses, identified stakeholder issues, and planned approaches to mitigate negative stakeholder reaction.

529. An output of the Identify Program Stakeholders process is a stakeholder management strategy. It captures mitigation approaches flowing from the identify Program Stakeholders process, which outlines the steps to take to manage the program’s impact on stakeholders.

530. The performance analysis report is prepared in the closing phase. It gathers final values and compares them with planned values for quality, cost, schedule, and resource data to determine program performance. The project manager uses data on stakeholder expectations and requirements to determine whether these requirements were met.

531. Constraints are factors that limit the program team’s options; typically, they affect schedule, cost, resources, or program deliverables. They are an input common to many program management processes and may restrict action.

532. The work breakdown structure (WBS) matrix is an output of the Develop Program WBS process. It is a graphical depiction of a deliverable or product- oriented grouping of work elements that is used to organize and subdivide the total work scope of the program.

533. Issues analysis is a tool and technique in the Manage Program Issues process. Such an analysis assesses the impact and severity of the issue, its root cause, and possible remedies.

534. Resource availability is an input to the Manage Program Resources process. It indicates availability of the personnel, assets, materials, or capital resources that are required to accomplish program goals and deliverables

535. Because risks and issues are components of the program management plan, a key result of the program life cycle during the Program Setup phase is Risk management consolidation. Program-level planning processes are key results of the Program Setup phase of the life cycle. One key process is risk management consolidation—that is, considering the risks of the various components of the program to address a key question in the program management plan: What are the risks and issues

536. In the Manage Component Interfaces process, the program architecture baseline is an input because it is the set of program components that outlines their characteristics, capabilities, deliverables, timing, and interfaces and how the components contribute to program benefits.

537. Focus groups are a tool and technique in the Identify Program Stakeholders process and are used to solicit feedback from stakeholder groups regarding their attitudes toward the program and appropriate approaches for impact mitigation. Open-ended questions help participants to interact with one another, thus resulting in a deeper understanding of program needs

538. Lessons learned updates are an output of the Distribute Information process and may include specific outputs of lessons learned activities, such as updates to the lessons learned repository; knowledge management databases; corporate policies, procedures, and processes; and risk management plan.

539. A key input to the Direct and Manage Program Execution process is the Program road map

540. In the face of this lack of common understanding of the requirements, you need to prepare a Program scope statement. The program scope statement is the basis for future program decisions and establishes the expectations of the endeavor. It articulates the scope of the program—generally, what is included and what is excluded. This is especially important if a stakeholder might erroneously assume that a particular product, service, or result is a program component

541. Updates to the program risk register are an output of the Monitor and Control Program Risks process. The risk monitoring program tracks the progress of each program risk and includes meeting minutes, actions implemented, and information on results. The project managers provide information about their projects to the program manager and other interested stakeholders.

542. Budget allocation reconciliation is a tool and technique in the Close Program Procurements process. Variations are typical in categorization, allocation, and summarization between program and program component plans, contracts, and organizational charts of account. These variations make it difficult to directly relate expenditures between different program and organization components

543. Your company mandates that each program have a governance board. As program manager, you meet with your board at the key decision points in your program’s life cycle. These phase-gate reviews are an opportunity to assess your program with respect to Delivery of program benefits.

544. Governance spans all program life cycle phases. A phase-gate reviews provides an objective assessment against the exit criteria of each phase to see whether the program should proceed to the next phase. They also allow you to assess the program on strategic alignments, investment appraisals, monitoring and control of opportunities and threats, benefits assessment, and monitoring of program outcomes

545. Planning is an iterative process. When a significant event affects the program and renders current plans inadequate or ineffective, the next step for a program manager is to revisit and update the plans to ensure their ongoing usefulness. This task is evident in both the Manage Program Architecture and the Manage Governance Infrastructure processes, the outputs of which are updated to the program management plan

546. Projects can be authorized during all phases of the life cycle except Program Closure. Programs consist of projects and ongoing activities. Projects can be authorized at any time throughout the program’s life cycle except in the Program Closure phase, when the phase-gate review has determined that all work in the program has been completed and benefits have accrued

547. During the Program Initiation phase, in the benefits life cycle, the components are derived and prioritized as the foundation of the program continues to develop, and a detailed road map is prepared. The benefits analysis and planning phase is where prioritization is done.

548. A contract management plan is prepared for significant purchases and acquisitions on programs to cover contract administration activities. It is prepared as an output of the Plan Program Procurements process, which
provides the guidelines for the Conduct Program Procurements process

549. The program’s funding method is determined during Establish Program Financial Framework processes. The purpose of the Establish Program Financial Framework process is to identify the overall financial environment
for the program and to pinpoint available funds according to identified milestones

550. Tolerances are a tool and technique in the Develop Program Management Plan process. They are ranges set for various aspects of the program such as time, cost, and scope. Without defined tolerances, the potential exists for conflicts over boundaries of authority

551. The contract closure procedure is a tool and technique in the Close Program Procurements process. It outlines the requirements for formally closing and/or terminating contractual agreements, including verification criteria to prevent the organization from contract breach. It ensures that all conditions are met and addresses any follow-on activities such as warranties and remedies

552. The Delivery of Program Benefits phase (phase four) is iterative and can be of unlimited duration. Each activity in this phase is repeated as often as needed, and the benefits accrue in a cumulative fashion. It ends only when the planned benefits have been achieved, delivered, and accepted or when the program is terminated

553. The program financial management plan is an output of the Develop Program Financial Plan process, which documents the program’s financial information, such as
  • Funding schedules and milestones,
  • The baseline budget,
  • contract payments and schedules,
  • Financial reporting processes and methods, and
  • Any financial metrics that are used
554. The program work breakdown structure (PWBS) does not replace the work breakdown structure (WBS) on each of the program’s projects. From a program perspective, the PWBS should be decomposed to the level of control that the program manager requires, which typically corresponds to the first one or two levels of the WBS of the component projects.

555. Monitor and Control Program Changes ensures that the appropriate level of governance is applied to decision making in regard to proposed changes to the program plan. During the Monitor and Control Program Changes process, decisions to accept, reject, or modify change requests are made by the people who have the designated authority to do so. As change decisions are made, the program team ensures that the changes are made to the program plan and communicated to the components for implementation or action.

556. Stakeholders play a critical role in program success. During program execution, the program manager must resolve issues and maintain the benefits register. As issues are resolved, the benefits register may require
updates. It is maintained during the benefits realization phase of the benefits management life cycle during the Delivery of Program Benefits phase of the program life cycle

557. Each organization has certain KPIs. Each program also has its own KPIs that should be aligned with the organization’s KPIs and objectives. These metrics can show how well the program is progressing according to the organization’s strategies.

558. Intangible benefits are difficult to quantify, although many contribute in a meaningful way to tangible benefits. Their contribution to business objectives must be assessed and the objectives must be stated in the most specific and measurable way possible

559. The Manage Component Interfaces process is ongoing throughout the program. Transparent management of interfaces is critical for scope adherence. It may trigger a need to redeploy resources as projects are
authorized. This is managed at the program level. Outputs from other processes and program-level documentation and records dealing with affected projects must be updated to reflect their new status

560. The program management plan is an input to the Close Program process. It is important to review it along with every subsidiary program plan to ensure that requirements have been met, final updates have been made, and any outstanding or active projects are brought to an orderly close

561. The Estimate to Complete is a forecasting technique; it is an estimate to complete the remaining work for an activity, program package, or control account. Such forecasting techniques are used in the Monitor and Control Program Financials process

562. To enable your program team to refine its communications strategy and tactics, you should consult the Program work breakdown structure (PWBS). As an input to the Distribute Information process, the PWBS is useful in communicating the program’s size and complexity as well as other characteristics.

563. Program governance is not a phase in the program management life cycle; rather, it spans all the life-cycle phases as it monitors the program’s progress and the delivery of benefits from the projects that are part of the program.

564. During the Program Initiation phase, the program components are defined. This phase may also include a high-level plan for all components

565. The benefits realization plan is prepared during the Program Initiation phase. It includes intended interdependencies of benefits being delivered by the various projects in the program.

566. Benefits are mapped into the program plan during the benefits analysis and planning phase, as the program management and technical infrastructure are established. Because the program plan is developed during the Program Setup phase, it is appropriate to map the benefits into the plan when the infrastructure is established.

567. The change request log is used to record, describe, or denote change requests. Any approved changes are accurately recorded in the log and are input to the Monitor and Control Program Changes and Distribute Information processes

568. The high-level program plan contains a clear statement of the program’s justification—that is, why it is important and what it needs to achieve.

569. The mission, vision, and strategic fit for the program must be aligned with the organization’s objectives. This is done as part of the Program Initiation phase. A statement of the program’s mission, vision, and strategic fit is included as part of the program charter, which is developed in the Program Initiation phase. The charter provides the authority to move forward to Program Setup.

570. During phase five of the program life cycle (the Program Closure phase), all program work has been completed and program benefits are accruing. A key activity in this phase is for the program manager to review the status of the benefits with stakeholders.

571. Benefits tend to be either tangible or intangible. Tangible benefits may be either financial or nonfinancial, but they can be quantified.

572. Program performance reports are inputs to the Provide Governance Oversight process. Such reports support program oversight and control so that the governance board can monitor program results and ensure that good practices are being followed.

573. program director is the individual with executive ownership of the program or programs.

574. The program sponsor is the group or person who champions the program initiative, is responsible for providing project resources, and ensures the ultimate delivery of program benefits.

575. The executive sponsor is the group or individual who is responsible for providing project resources and ultimately for ensuring program success. The executive sponsor is appointed in the Program Initiation phase

576. A program has three major communications channels:
  • Clients,
  • Sponsors, and
  • Component managers
577. Parkinson’s law states that work expands to fill the amount of time allocated for it. If a project manager has padded the schedule stating that work will take 25 weeks to complete then work will actually take 25 weeks to complete

578. Configuration management system is the component of the change management system, which is responsible for evaluating, testing and documenting changes related to the project scope

579. When a change request is made that will affect the project scope, the Configuration management system evaluates the change requests and documents the features and functions of the change on the project scope

580. Step funding is incremental funding based on the program performance. It is called step funding because on the S-curve the funding looks like stair steps from milestone to milestone

581. Phase gate estimating is the estimation of the cost of each phase just before the phase is set to begin

582. As a program manager, the only role you will play during a project manager’s project closure, is to ensure that the projects within the program have been closed at the project level

583. When there are clarifications in the bidder’s conference, the statement of work (SOW) should be updated. When appropriate you should also update the request for proposal documentation

584. One benefit of creating a program is that it provides centralized risk management

585. For internal projects, project initiator or project sponsor provides the SOW based on business needs, product or service requirements

586. For external projects, SOW can be received from the customer as part of a bid document

587. Project manager is trying to get formal acceptance and sign-off document for the project. But the customer is not willing to do and is complaining about the inferior product. Project manager would have avoided this situation if taken following actions
  • Documenting the requirements
  • Performing quality inspections time to time
  • Requesting sign-off at important milestones
588. The process of delivering the program benefits as they were promised to operations is the direct and manage program execution

589. Program Manager is creating a document that defines the benefits the program will create for the Organization once the program has been completed. This document is program benefits statement

590. Program benefits statement defines all the benefits the program will create for the Organization. The benefits statement is mapped to the strategy of the organization and benefits management within the program

591. A claim is a documented disagreement between the vendor and the buyer where one party (and sometimes both) disagrees with the conditions, performance or payments. The contract should always have the escalation process defined should litigation between the parties arise

592. A benefit is an outcome of actions and behaviors that provides utility to stakeholders

593. A portfolio is a term to describe the operations, projects, and programs that are related by discipline, application area, or expected outcomes

594. The project management lifecycle is universal to all projects and the project lifecycle is unique to unique to each project

595. Quality assurance is a prevention-driven process to plan the work properly and completely in an effort to do the work correctly the first time

596. Each project in your program will require its own charter. The project charter defines the project manager and their level of authority over the project resources

597. The Critical Chain Method for scheduling activities considers the availability of project resources to determine if the resources are actually available before creating the sequence of project activities

598. A resource histogram is a bar chart that shows the utilization of selected resources within a defined time frame, such as weeks, months, or quarters

599. You consider following factors while deciding to use internal or external staff
  • Length of time particular skill set is required
  • Availability of internal resources
  • Cost of external resources and
  • Timing of the need
600. Strategic objectives and expected benefits are the key Program selection criteria

601. One key result from the program initiation phase is to identify those persons who should be members of the program board. This occurs after the program charter has been approved

PMBOK4 Notes are shared under My Notes on PMBOK V4

I will continue sharing SPM V1 notes in my next post

7 comments:

  1. Someone asked me a question

    Could you please help me in linkage between program lifecycle (Pre program Setup , Program Setup……program Closure) and Program Process Group (Initiation, Planning…..closure)
    I personnel feel that there is no 1 to 1 relation ship with both of them. But then how to link program lifecycle with Program Process group


    I will let others chime in but my answer was

    Let me see if I can help answer your question. Note that this is going to be my interpretation and you can double check by posting to others. Program Lifecycle runs throughout the program and within each stage, one can have one or more or all process groups applied. Let me elaborate. Say you are in Program Set up stage. Purpose of program setup phase is to progressively elaborate the program charter and develop the foundation for the program by establishing an infrastructure and building a detailed “roadmap” that provides direction on how the program will be managed and defines its key deliverables.
    So in this stage of lifecycle, you can go through all program process groups of IPECC. You can initiate elaboration of program charter, do planning, execute the plan, monitor and control and finally have a closure.

    ReplyDelete
  2. Good Job.

    I think it will be better if you can include it in one PDF file.

    ReplyDelete
  3. this is great information. thank you.
    will it be possible to share sample experience summaries for the 5 areas of program management? it will help a lot in the PgMP application process

    ReplyDelete
  4. Thanks for this blog Sridhar. ! personally learnt a lot for PMP and ACP certification. Awaiting PgMP now..

    ReplyDelete